Converting p6 file to ms project









Click Next to review the settings for your export.The template contains options for exchanging data with Microsoft Project. Add a new template or modify the existing template (if necessary).Double click in the Export File Name field if you want to change the name and location of the Microsoft Project file. Mark the Export checkbox of all projects you want to export.Select the type of file to which you want to export.MPX - for an export to Microsoft Project 2002.XML 2013- for an export to Microsoft Project 2013.XML 2010- for an export to Microsoft Project 2010.XML 2007- for an export to Microsoft Project 2007.

converting p6 file to ms project

  • XML 2003- for an export to Microsoft Project 2003.
  • converting p6 file to ms project

    From the pull-down menu, select one of the following options:.











    Converting p6 file to ms project